| BID TABULATION | |||||
| 53-18AUG05 Sheriff's Department North Substation Site Work | |||||
| Christensen Construction Co. | |||||
| Description | Qty | Unit | Unit Price | Extended Price | |
| Mobilization | 1 | LS | $3,500.00 | $3,500.00 | |
| Earthwork | 460 | CY | $8.00 | $3,680.00 | |
| Silt Fence | 400 | LF | $4.50 | $1,800.00 | |
| Erosion Control Mat (Ditch Liner) | 115 | SY | $6.00 | $690.00 | |
| 2 1/2" Compact Aggregate Base (4" thickness) | 890 | SY | $3.76 | $3,346.40 | |
| 1 1/2" Compacted Aggregate Base (4" thickness) | 849 | SY | $3.76 | $3,192.24 | |
| Two (2) applications of Chip & Seal Surfacing | 808 | SY | $6.58 | $5,316.64 | |
| Unsuitable Subgade Repair | 10 | CY | $50.00 | $500.00 | |
| Base Bid Total | $22,025.28 | ||||