Bid Tabulation


                 
70-07OCT03 - Applewood Creek Neighborhood Improvement Project
Christensen Const. C.L. Richardson Const.    
Page #  Description of Work Unit # of Units Unit Price  Cost Unit Price  Cost    
5.1. Moblization  LS 1 $2,800.00 $2,800.00 $1,940.00 $1,940.00    
  Clearing & Grubbing LS 1 $7,200.00 $7,200.00 $3,125.00 $3,125.00    
  Linear Grading LF 2,080 $3.50 $7,280.00 $3.45 $7,176.00    
  Type 1 Aggregate Base (Rollstone) for Roadway, 1" average on Applewood Creek Rd. and 2" average on Crabapple & Persimmon Roads except for where raodway is widened, which will be 4" (in widened area only) TON 400 $20.80 $8,320.00 $23.70 $9,480.00    
  Type 1 Aggregate Base (Rollstone) for Driveway Transistions and Shoulder Rock where Required TON 150 $20.80 $3,120.00 $32.65 $4,897.50    
  Type 2 Aggregate Base (Rollstone) for Roadway Buildup in areas outside existing roadbed TON 380 $20.80 $7,904.00 $14.50 $5,510.00    
  Asphalt Plant Bituminous Base (3½") TON 1,000 $44.20 $44,200.00 $45.70 $45,700.00    
  Asphalt Surface (1½") TON 410 $44.20 $18,122.00 $47.25 $19,372.50    
  18" CMP w/ 3:1 mitered end sections (included in L.F.) LF 66 $35.00 $2,310.00 $60.25 $3,976.50    
  Concrete Milling LF 20 $25.00 $500.00 $11.90 $238.00    
  Restoration LS 1 $3,500.00 $3,500.00 $1,900.00 $1,900.00    
  Traffic Control LS 1 $1,500.00 $1,500.00 $525.00 $525.00    
  Total       $106,756.00   $103,840.50    
3.1 Completion of Bidder's Qualifications   Yes Yes      
6.1 Anti Collusion Statement   Yes Yes      
7.1. Signature and Identity of Bidder   Yes Yes      
8.1 Bidder's Acknowledgment   Yes Yes      
  Bid Bond   Yes Yes      
  Addendum   Yes Yes